Raceway installed and starting to set targets and air hose.
Friday, September 10, 2010
Thursday, September 9
Targets are built and raceway is being installed.
Adam's Report - Yesterday we cut all the flex and airline for the targetry. Also put all targetry and mounting stands together. We put together the raceway to mount on the back of the kneewall. Today we installed raceway on shooters right, laid all the 18/6 wire out to be pulled through conduit.
All trash is piled for inmates to remove. This has been coordinated with USP for pickup.
Adam's Report - Yesterday we cut all the flex and airline for the targetry. Also put all targetry and mounting stands together. We put together the raceway to mount on the back of the kneewall. Today we installed raceway on shooters right, laid all the 18/6 wire out to be pulled through conduit.
All trash is piled for inmates to remove. This has been coordinated with USP for pickup.
Thursday, September 9, 2010
Work started Tuesday, September 7
Parts are on site and being inventoried. Concrete and control room shed not built and may not be finished before the end of the week. We may have to pull off project and return at a later date.